SC
Sarah Collins
Senior H&S Consultant, CMIOSH
Register
RA-2026-1784
Roof Work – Midland Roofing & Cladding Ltd
Riverside Retail Park re-roof · Assessor Sarah Collins · Reviewer James Whitfield
Summary
- Status
- Approved
- Highest residual risk
- 10High
- Created
- 12 Nov 2026
- Review date
- 12 Nov 2027
- Time taken
- 2h 40m (AI-assisted)
- Version
- 1.0
Version history
- v1.0 · 17 Nov 2026Gareth Morgan (client)Approved by client via portal
- v1.0 · 14 Nov 2026James WhitfieldSenior review approved
- v0.2 · 13 Nov 2026James WhitfieldReturned: add roof-light covers & netting sign-off to row 2
- v0.1 · 12 Nov 2026Sarah CollinsAI draft generated from site visit (2h 40m total)
13-column risk assessment
| Ref | Activity / Task | Hazard | Who might be harmed & how | Existing control measures | S | L | Initial risk | Additional control measures | Res. S | Res. L | Residual risk | Action by / Date | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Strip & re-sheet industrial profile roof | Fall from roof edge | Roofers – fatal or major injury | Scaffold edge protection to eaves | 5 | 3 | 15 | Double guard rail & toe board on all open edges; gable-end protection | 5 | 1 | 5 | Site supervisor / 02/12/2026 | |
| 2 | Strip & re-sheet industrial profile roof | Fall through fragile roof sheets or roof lights | Roofers – fatal injury | Fragile roof signage | 5 | 4 | 20 | Safety netting beneath; roof light covers; crawling boards; no-go zones marked | 5 | 2 | 10 | Site supervisor / 05/12/2026 | |
| 3 | Strip & re-sheet industrial profile roof | Disturbance of asbestos-containing materials | Operatives & occupants – mesothelioma | Asbestos register reviewed | 5 | 2 | 10 | Refurbishment survey; licensed contractor for removal; stop-work procedure | 5 | 1 | 5 | Site supervisor / 08/12/2026 | |
| 4 | Strip & re-sheet industrial profile roof | Adverse weather (high wind, ice, rain) | Roofers – slips & falls; materials blown | Supervisor checks forecast | 4 | 3 | 12 | Stop work at wind speeds above 23mph (Beaufort 5); secure loose sheets | 3 | 1 | 3 | Site supervisor / 11/12/2026 | |
| 5 | Strip & re-sheet industrial profile roof | Manual handling of roofing materials | Operatives – musculoskeletal injury | Two-person lifts | 3 | 3 | 9 | Mechanical hoist / loading bay; reduced pack sizes | 2 | 1 | 2 | Site supervisor / 14/12/2026 | |
| 6 | Strip & re-sheet industrial profile roof | Hot works – torch-on felt | Operatives & building – burns, fire | Fire extinguisher on roof | 4 | 2 | 8 | Hot works permit; 1-hour fire watch after completion | 3 | 1 | 3 | Site supervisor / 17/12/2026 |
Approved assessments are locked. Duplicate to create a revision.
Review comments
James Whitfield on row 2 · 13 Nov 2026
Please specify netting installer (FASET) and roof-light covers before work starts.
Sarah Collins on row 2 · 13 Nov 2026
Updated – FASET-qualified installer named in additional controls.
Sign-off
- Assessor
- Sarah Collins
- Senior reviewer
- James Whitfield
- Client representative
- Gareth Morgan
- Operatives acknowledged
- Liam Reece, Josh Abbott, Kieran Doyle